The Situation
A national retailer faced the need to optimize its store footprint, requiring the closure of approximately 15% of its locations within a tight timeline. The company engaged NEST to oversee this complex, multi-phase project.
With store closures spanning nearly every state, including remote locations such as Hawaii and Alaska, NEST had to ensure a seamless transition while minimizing disruption and maintaining cost efficiency.
The NEST Solution
NEST implemented a structured project management framework that emphasized communication, provider sourcing, risk mitigation, and budget control.
The key components of NEST’s approach included:
Project Planning & Timeline Coordination
- Initial client communication began in early December with a preliminary store list of closures that would take place the following month.
- Work orders were divided into three phases, requiring rapid response and real-time adjustments.
- The project officially launched in early January, with all closures completed within a four-week timeframe.
- Over 60 providers were engaged for fixture removal, signage dismantling, trash management, and more.
- NEST conducted a risk analysis to identify service gaps in remote or challenging markets.
- NEST tapped into its network of service providers to ensure nationwide coverage, with particular attention to high-risk locations such as Hawaii.
- NEST leveraged mass communication tools to streamline vendor outreach.
- Work orders were systematically dispatched via NEST Facilitate, allowing real-time tracking and adjustments.
- Twice-weekly check-ins ensured all stakeholders remained aligned on progress and challenges.
Execution & Adaptability
- 800 total work orders were completed, covering both signage and trash removal.
- An average of 32 work orders per day were processed to meet the ambitious deadline.
- Weather-related challenges, particularly in colder regions, required contingency planning and proactive client communication.
- Mall locations posed additional logistical hurdles due to varying landlord requirements for COIs, scheduling, and disposal restrictions, which NEST managed seamlessly.
The Results
Through strategic execution and a collaborative approach, NEST successfully delivered:
- The closure of nearly 400 stores across 46 states within a four-week period.
- A 6% savings on the proposed budget, delivering cost efficiencies for the client.
- Effective vendor partnerships ensured work was completed on time and in compliance with all local regulations.
- A process that was structured yet flexible enough to adapt to changing conditions, including last-minute store list adjustments and environmental challenges.
While NEST is typically engaged in helping retailers expand, this project demonstrated its ability to manage large-scale store closures with the same level of precision and efficiency. By leveraging its extensive provider network, technology-driven coordination, and meticulous project management, NEST ensured a seamless execution that supported the client’s long-term strategic goals.